37000 Feet | Browse and search NASA's Aviation Safety Reporting System |
|
Attributes | |
ACN | 1744964 |
Time | |
Date | 202006 |
Local Time Of Day | 1201-1800 |
Place | |
Locale Reference | HPN.Airport |
State Reference | NY |
Environment | |
Flight Conditions | VMC |
Light | Daylight |
Aircraft 1 | |
Make Model Name | Small Transport |
Operating Under FAR Part | Part 91 |
Flight Phase | Climb |
Flight Plan | IFR |
Person 1 | |
Function | Captain Pilot Not Flying |
Qualification | Flight Crew Air Transport Pilot (ATP) Flight Crew Multiengine Flight Crew Instrument |
Events | |
Anomaly | ATC Issue All Types Deviation - Procedural Clearance Deviation - Track / Heading All Types |
Narrative:
Sic obtained a hold for release clearance; and loaded the FMS. Reviewed FMS programming per fom/aom verified all the points. Sic stated we were given a SID then as filed. While proceeding on our route; ATC cleared us to a fix that was not on our flight plan. Queried ATC as to our routing; and it did not match our as filed routing. (Filed zzzzz jxxx ZZZ1 ZZZ2 jxxy ZZZ4; believe ATC said clearance was zzzzz jxxx ZZZ3 direct ZZZ4). Asked ATC for a heading while we corrected our FMS programming. ATC cleared us to another fix; verified the routing to destination. We adjusted the routing and proceeded to our destination.re-opening the ATC facilities at hpn would be helpful; especially with the increasing amount of flights into and out of hpn.
Original NASA ASRS Text
Title: Pilot reported clearance was different than what they had filed and would like to see HPN ATC Facilities re-open.
Narrative: SIC obtained a hold for release clearance; and loaded the FMS. Reviewed FMS programming per FOM/AOM verified all the points. SIC stated we were given a SID then as filed. While proceeding on our route; ATC cleared us to a fix that was not on our flight plan. Queried ATC as to our routing; and it did not match our as filed routing. (Filed ZZZZZ JXXX ZZZ1 ZZZ2 JXXY ZZZ4; believe ATC said clearance was ZZZZZ JXXX ZZZ3 direct ZZZ4). Asked ATC for a heading while we corrected our FMS programming. ATC cleared us to another fix; verified the routing to destination. We adjusted the routing and proceeded to our destination.Re-opening the ATC facilities at HPN would be helpful; especially with the increasing amount of flights into and out of HPN.
Data retrieved from NASA's ASRS site and automatically converted to unabbreviated mixed upper/lowercase text. This report is for informational purposes with no guarantee of accuracy. See NASA's ASRS site for official report.