Time | |
Date | 200201 |
Day | Tue |
Local Time Of Day | 0601 To 1200 |
Place | |
Locale Reference | airport : zzz.airport |
State Reference | US |
Altitude | agl single value : 0 |
Aircraft 1 | |
Operator | common carrier : air carrier |
Make Model Name | A300 |
Operating Under FAR Part | Part 121 |
Flight Phase | ground : parked ground : maintenance |
Person 1 | |
Affiliation | company : air carrier |
Function | maintenance : technician |
Qualification | technician : powerplant technician : airframe |
ASRS Report | 534904 |
Person 2 | |
Affiliation | company : air carrier |
Function | other personnel other |
Events | |
Anomaly | aircraft equipment problem : less severe other anomaly other |
Independent Detector | other other : 1 |
Resolutory Action | other |
Consequence | other |
Factors | |
Maintenance | contributing factor : schedule pressure contributing factor : non availability of parts performance deficiency : logbook entry |
Supplementary | |
Problem Areas | Maintenance Human Performance Aircraft |
Primary Problem | Maintenance Human Performance |
Narrative:
Aircraft X's APU was replaced on late night shift and I took a turnover on jan/sun/02. The APU exhaust muffler bellows is deteriorated. The bellows couples the APU exhaust to the exhaust duct. The APU change work card was stopped at the step where the exhaust bellows is connected. The remaining steps are open including the final inspection rii. I was advised by maintenance operations to enter in the fmr that the work card wasn't completed. I did what he requested. I discussed this with ovhl quality assurance and ovhl technician foreman. They agree this wasn't proper. Basically, the aircraft has a major component replaced and the paperwork wasn't completed and could become a safety hazard if anyone tried to start the APU. The modification disagreed and the aircraft routing was changed and still has not been repaired and the paperwork is still incomplete.
Original NASA ASRS Text
Title: AN AIRBUS 300 TECHNICIAN RPTS REPLACING AN APU BUT NOT COMPLETING THE LAST 2 JOB CARD STEPS. MAINT CTLR DEFERRED THE APU INOP PER MEL.
Narrative: ACFT X'S APU WAS REPLACED ON LATE NIGHT SHIFT AND I TOOK A TURNOVER ON JAN/SUN/02. THE APU EXHAUST MUFFLER BELLOWS IS DETERIORATED. THE BELLOWS COUPLES THE APU EXHAUST TO THE EXHAUST DUCT. THE APU CHANGE WORK CARD WAS STOPPED AT THE STEP WHERE THE EXHAUST BELLOWS IS CONNECTED. THE REMAINING STEPS ARE OPEN INCLUDING THE FINAL INSPECTION RII. I WAS ADVISED BY MAINT OPS TO ENTER IN THE FMR THAT THE WORK CARD WASN'T COMPLETED. I DID WHAT HE REQUESTED. I DISCUSSED THIS WITH OVHL QUALITY ASSURANCE AND OVHL TECHNICIAN FOREMAN. THEY AGREE THIS WASN'T PROPER. BASICALLY, THE ACFT HAS A MAJOR COMPONENT REPLACED AND THE PAPERWORK WASN'T COMPLETED AND COULD BECOME A SAFETY HAZARD IF ANYONE TRIED TO START THE APU. THE MODIFICATION DISAGREED AND THE ACFT ROUTING WAS CHANGED AND STILL HAS NOT BEEN REPAIRED AND THE PAPERWORK IS STILL INCOMPLETE.