Narrative:

In the process of performing maintenance on air force C17 core thrust reversers. We have been informed that the primary job planning card being used was intended to be a 'guide' to base the development of procedures proper to air carrier. It seems these 'proper' procedures were never developed. Therefore, 'proper' policies have not been followed for approximately 8 months. The job accomplishment, quality, and airworthiness have 'not' been compromised in any way. The paper package being used in AFB works there, but not at air carrier company.

Google
 

Original NASA ASRS Text

Title: A SHOP TECHNICIAN RPTS C17 CORE THRUST REVERSERS ARE BEING PREPARED USING A PRIMARY JOB PLANNING CARD AND NOT A FULLY DEVELOPED JOB CARD.

Narrative: IN THE PROCESS OF PERFORMING MAINT ON AIR FORCE C17 CORE THRUST REVERSERS. WE HAVE BEEN INFORMED THAT THE PRIMARY JOB PLANNING CARD BEING USED WAS INTENDED TO BE A 'GUIDE' TO BASE THE DEVELOPMENT OF PROCS PROPER TO ACR. IT SEEMS THESE 'PROPER' PROCS WERE NEVER DEVELOPED. THEREFORE, 'PROPER' POLICIES HAVE NOT BEEN FOLLOWED FOR APPROX 8 MONTHS. THE JOB ACCOMPLISHMENT, QUALITY, AND AIRWORTHINESS HAVE 'NOT' BEEN COMPROMISED IN ANY WAY. THE PAPER PACKAGE BEING USED IN AFB WORKS THERE, BUT NOT AT ACR COMPANY.

Data retrieved from NASA's ASRS site as of July 2007 and automatically converted to unabbreviated mixed upper/lowercase text. This report is for informational purposes with no guarantee of accuracy. See NASA's ASRS site for official report.