Narrative:

While on approach to iah I noted a power loss on the #1 engine. I called for the engine flameout checklist. It appeared to restart. The torque then dropped to zero and the nh was decreasing. I then called for the engine fire/failure checklist and the engine was secured. While I continued the approach, the first officer completed the QRH items. I notified ATC, the flight attendant, and the passenger of the engine shutdown. The aircraft was landed and the passenger deplaned without incident.

Google
 

Original NASA ASRS Text

Title: ATR42-320 ACFT ON LONG APCH HAD #1 ENG FAILURE. CHKLIST WAS COMPLETED WITH ENG SHUTDOWN, ATC AND PAX NOTIFIED WITH UNEVENTFUL LNDG.

Narrative: WHILE ON APCH TO IAH I NOTED A PWR LOSS ON THE #1 ENG. I CALLED FOR THE ENG FLAMEOUT CHKLIST. IT APPEARED TO RESTART. THE TORQUE THEN DROPPED TO ZERO AND THE NH WAS DECREASING. I THEN CALLED FOR THE ENG FIRE/FAILURE CHKLIST AND THE ENG WAS SECURED. WHILE I CONTINUED THE APCH, THE FO COMPLETED THE QRH ITEMS. I NOTIFIED ATC, THE FLT ATTENDANT, AND THE PAX OF THE ENG SHUTDOWN. THE ACFT WAS LANDED AND THE PAX DEPLANED WITHOUT INCIDENT.

Data retrieved from NASA's ASRS site as of July 2007 and automatically converted to unabbreviated mixed upper/lowercase text. This report is for informational purposes with no guarantee of accuracy. See NASA's ASRS site for official report.