Narrative:

At the end of 20 hours of training in the repair and overhaul of this valve, I made 3 valves svcable and returned them to stock. At that time, I reviewed the joint document and realized that some of the testing required to make a unit svcable after overhaul had not been accomplished. I asked my trainer about it and was told that we did not have the equipment to perform all the tests. I then went to my lead wxvx and he and I informed our team leader XXXZ of the situation. She ordered us to hold all the other units I was working on OTS pending a review by the engineering department.

Google
 

Original NASA ASRS Text

Title: AN OVERHAUL SHOP RPTS P&W 2000 ENGS DURING #4 BEARING SCAVENGE VALVE OVERHAULS ARE NOT TESTED PER VENDOR'S MANUAL DUE LACK OF TEST EQUIP.

Narrative: AT THE END OF 20 HRS OF TRAINING IN THE REPAIR AND OVERHAUL OF THIS VALVE, I MADE 3 VALVES SVCABLE AND RETURNED THEM TO STOCK. AT THAT TIME, I REVIEWED THE JOINT DOCUMENT AND REALIZED THAT SOME OF THE TESTING REQUIRED TO MAKE A UNIT SVCABLE AFTER OVERHAUL HAD NOT BEEN ACCOMPLISHED. I ASKED MY TRAINER ABOUT IT AND WAS TOLD THAT WE DID NOT HAVE THE EQUIP TO PERFORM ALL THE TESTS. I THEN WENT TO MY LEAD WXVX AND HE AND I INFORMED OUR TEAM LEADER XXXZ OF THE SIT. SHE ORDERED US TO HOLD ALL THE OTHER UNITS I WAS WORKING ON OTS PENDING A REVIEW BY THE ENGINEERING DEPT.

Data retrieved from NASA's ASRS site as of July 2007 and automatically converted to unabbreviated mixed upper/lowercase text. This report is for informational purposes with no guarantee of accuracy. See NASA's ASRS site for official report.