Narrative:

Aircraft X was told to land runway 16 and that aircraft Y would land runway 11 and hold short of runway 16. Aircraft Y acknowledge lahso; but went around over aircraft X as it was exiting the runway. Lahso was on the ATIS.recommendation; runway 11 needs to be extended on the approach end so lahso can be done safely.

Google
 

Original NASA ASRS Text

Title: HPN Controller described a failed LAHSO when traffic landing Runway 11 elected to go around; over flying traffic [that] was rolling out on Runway 16.

Narrative: Aircraft X was told to land Runway 16 and that Aircraft Y would land Runway 11 and hold short of Runway 16. Aircraft Y acknowledge LAHSO; but went around over Aircraft X as it was exiting the runway. LAHSO was on the ATIS.Recommendation; Runway 11 needs to be extended on the approach end so LAHSO can be done safely.

Data retrieved from NASA's ASRS site as of April 2012 and automatically converted to unabbreviated mixed upper/lowercase text. This report is for informational purposes with no guarantee of accuracy. See NASA's ASRS site for official report.