37000 Feet | Browse and search NASA's Aviation Safety Reporting System |
|
Attributes | |
ACN | 633094 |
Time | |
Date | 200410 |
Day | Sun |
Local Time Of Day | 1201 To 1800 |
Place | |
Locale Reference | airport : zzz.airport |
State Reference | US |
Altitude | agl single value : 0 |
Environment | |
Light | Daylight |
Aircraft 1 | |
Operator | common carrier : air carrier |
Make Model Name | MD-80 Series (DC-9-80) Undifferentiated or Other Model |
Operating Under FAR Part | Part 121 |
Flight Phase | ground : maintenance |
Person 1 | |
Affiliation | company : air carrier |
Function | other personnel other |
ASRS Report | 633094 |
Person 2 | |
Affiliation | company : air carrier |
Function | other personnel other |
Events | |
Anomaly | aircraft equipment problem : less severe maintenance problem : improper documentation non adherence : far non adherence : published procedure |
Independent Detector | other other : 1 |
Resolutory Action | none taken : detected after the fact |
Consequence | other other |
Factors | |
Maintenance | contributing factor : non availability of parts |
Supplementary | |
Problem Areas | Environmental Factor Maintenance Human Performance Chart Or Publication Aircraft |
Primary Problem | Maintenance Human Performance |
Narrative:
Due to problems of communication earlier in the shipping department (who picks up parts at terminal and tlo) an unnecessary delay resulted in movement of a critical part. The directive was given to deliver part straight to hangar #2 by the manager and supervisor at dock. However, this action resulted in the part not being checked, verified, logged or processed into the system by the stores person assigned to aircraft overhaul work unit resulting in improper and incomplete paperwork in our system and in the bill of works for that aircraft.
Original NASA ASRS Text
Title: AN MD80 INCURRED AN AVOIDABLE DELAY DUE TO PARTS ORDERING PROCS NOT FOLLOWED. CRITICAL PART DELIVERED TO WRONG AREA.
Narrative: DUE TO PROBS OF COM EARLIER IN THE SHIPPING DEPT (WHO PICKS UP PARTS AT TERMINAL AND TLO) AN UNNECESSARY DELAY RESULTED IN MOVEMENT OF A CRITICAL PART. THE DIRECTIVE WAS GIVEN TO DELIVER PART STRAIGHT TO HANGAR #2 BY THE MGR AND SUPVR AT DOCK. HOWEVER, THIS ACTION RESULTED IN THE PART NOT BEING CHKED, VERIFIED, LOGGED OR PROCESSED INTO THE SYS BY THE STORES PERSON ASSIGNED TO ACFT OVERHAUL WORK UNIT RESULTING IN IMPROPER AND INCOMPLETE PAPERWORK IN OUR SYS AND IN THE BILL OF WORKS FOR THAT ACFT.
Data retrieved from NASA's ASRS site as of July 2007 and automatically converted to unabbreviated mixed upper/lowercase text. This report is for informational purposes with no guarantee of accuracy. See NASA's ASRS site for official report.