Narrative:

Contacted maintenance planner in ZZZ that task intervals for cis not recorded properly. Engineering order X (part B) was complied with and paperwork facsimile'ed and routed as required. Upon inspection; found crack requiring inspection to be conducted at 65 hour intervals. Research idented that crack was previously found on mar/tue/06 in ZZZ which would require the inspection at 65 hour intervals and compliance of engineering order X.

Google
 

Original NASA ASRS Text

Title: A DHC8-400 DURING A BORESCOPE INSPECTION OF LOW PRESSURE COMPRESSOR SUPPORT FOUND A CRACK THAT WAS ALREADY RPTED BUT NOT ENTERED ON 65 HR REQUIRED INTERVAL INSPECTION.

Narrative: CONTACTED MAINT PLANNER IN ZZZ THAT TASK INTERVALS FOR CIS NOT RECORDED PROPERLY. ENGINEERING ORDER X (PART B) WAS COMPLIED WITH AND PAPERWORK FAX'ED AND ROUTED AS REQUIRED. UPON INSPECTION; FOUND CRACK REQUIRING INSPECTION TO BE CONDUCTED AT 65 HR INTERVALS. RESEARCH IDENTED THAT CRACK WAS PREVIOUSLY FOUND ON MAR/TUE/06 IN ZZZ WHICH WOULD REQUIRE THE INSPECTION AT 65 HR INTERVALS AND COMPLIANCE OF ENGINEERING ORDER X.

Data retrieved from NASA's ASRS site as of January 2009 and automatically converted to unabbreviated mixed upper/lowercase text. This report is for informational purposes with no guarantee of accuracy. See NASA's ASRS site for official report.