37000 Feet | Browse and search NASA's Aviation Safety Reporting System |
|
Attributes | |
ACN | 687292 |
Time | |
Date | 200601 |
Place | |
Locale Reference | airport : zzz.airport |
State Reference | US |
Altitude | agl single value : 0 |
Aircraft 1 | |
Operator | common carrier : air carrier |
Make Model Name | B777 Undifferentiated or Other Model |
Operating Under FAR Part | Part 121 |
Flight Phase | ground : maintenance |
Person 1 | |
Affiliation | company : air carrier |
Function | maintenance : technician |
ASRS Report | 687292 |
Person 2 | |
Affiliation | company : air carrier |
Function | maintenance : inspector |
Events | |
Anomaly | aircraft equipment problem : critical maintenance problem : improper documentation maintenance problem : improper maintenance non adherence : published procedure non adherence : far |
Independent Detector | other other : 2 |
Resolutory Action | none taken : detected after the fact |
Consequence | other other |
Factors | |
Maintenance | contributing factor : work cards contributing factor : engineering procedure performance deficiency : scheduled maintenance performance deficiency : non compliance with legal requirements |
Supplementary | |
Problem Areas | Aircraft Maintenance Human Performance Chart Or Publication |
Primary Problem | Maintenance Human Performance |
Narrative:
Was assigned to the hangar to perform engineering change order per service bulletin X and may have inadvertently loosened a bolt not part of work required. Was later informed of service bulletin X where they are replacing the bolt with a hex head bolt versus the same bolt with the same head as the rest. Have become aware of service bulletin X and further reviewed the service bulletin so this will not occur again.
Original NASA ASRS Text
Title: A TECHNICIAN WORKING AN ENGINEERING CHANGE ORDER ON AN RB211 ENG GEAR BOX INADVERTENTLY LOOSENED A BOLT THAT WAS NOT PART OF THE CHANGE ORDER.
Narrative: WAS ASSIGNED TO THE HANGAR TO PERFORM ENGINEERING CHANGE ORDER PER SVC BULLETIN X AND MAY HAVE INADVERTENTLY LOOSENED A BOLT NOT PART OF WORK REQUIRED. WAS LATER INFORMED OF SVC BULLETIN X WHERE THEY ARE REPLACING THE BOLT WITH A HEX HEAD BOLT VERSUS THE SAME BOLT WITH THE SAME HEAD AS THE REST. HAVE BECOME AWARE OF SVC BULLETIN X AND FURTHER REVIEWED THE SVC BULLETIN SO THIS WILL NOT OCCUR AGAIN.